Comment on FR Doc # 2026-12562
National Defense Industrial AssociationOtherTrade association
Summary: The National Defense Industrial Association (NDIA) provides comments on proposed updates to FAR Parts 3 and 49. They argue that the proposed 60-day timeline for technical data marking evidence is too short for complex procurements and that the 90-day deadline for termination settlement proposals is insufficient without reducing the required information.